Sadawarna Dam construction progress reaches 90%

13 July 2022 11:51

JAKARTA - The Ministry of Public Works and Public Housing (PUPR) is completing the construction of the Sadawarna Dam in Subang Regency, West Java, which prioritizes the concept of green natural recycling. Environmentally-based and sustainable infrastructure principles were applied to the construction of the Sadawarna Dam starting from the survey, investigation, design, land acquisition, construction, to operation and maintenance (SIDLACOM) stages.

In the construction of the Sadawarna Dam, the Ministry of PUPR through the Citarum River Basin Center (BBWS), the Directorate General (Ditjen) of Water Resources, optimizes the potential function of the dam by promoting 7 concepts of green natural recycle.

"Currently, the need for solar cells is being calculated. Incidentally, the current utilization as an operational supply is around 70 thousand Watt, but in the future it will not only be internal but also external," said Head of BBWS Citarum, Ministry of PUPR Bastari.

The Sadawarna Dam was built from the start of the contract in November 2018 with a total APBN cost of IDR 2 trillion. The construction is divided into two packages, namely the first package carried out by Joint Operations (KSO) PT. Wijaya Karya - PT Daya Mulia Turangga - PT Barata Indonesia with 93.76% progress of work until July 4, 2022 and Package II is being carried out by KSO PT. Nindya Karya – PT Adhi Karya with progress reaching 87.50%. (LM)

© 2024 - IDN Financials - All Rights Reserved.