JAKARTA - PT Adhi Karya (Persero) Tbk (ADHI) obtained a work contract for the construction of the MRT railways from PT Mass Rapid Transit (MRT) Jakarta worth Rp 4.03 trillion. The time to carry out this project for the next 58 months.

As quoted from the disclosure of company information, Monday (17/2), Parwanto Noegroho, Corporate Secretary of PT Adhi Karya (Persero) Tbk (ADHI) said the scope of work includes the design of building underground buildings in the Sarinah and Monas area. Including, electrical substations and all mechanical and electrical work on the station building.

In working on the project, the portion of Adhi Karya was 35% and Shimizu Corporation 65%. The Jakarta Phase 2 MRT project includes the CP 201 contract package; underground buildings and civil works 1. (LK)