PUPR Ministry completes the construction of Cisangkuy Floodway

04 December 2020 09:31

JAKARTA - Entering the rainy season at the end of 2020, the Ministry of Public Works and Housing (PUPR) has completed the construction of the Cisangkuy Floodway.

"The Cisangkuy Floodway is a floodway to enter the Citarum River at the downstream of Dayeuhkolot, which regularly floods. We will flow the flood discharge to the Cisangkuy Floodway for about 200 m3 / second so that only 5 m3 / second passes through the original Cisangkuy River. This will reduce the load on the Citarum River in Dayeuhkolot,” said Minister Basuki.

The construction of the Cisangkuy Floodway is carried out in 2 packages, namely package 1 with a length of 3.75 km with a budget of Rp 311.53 billion with a capacity of 230 m3 / second. Package 1 work is carried out under a 2015-2020 multi-year contract by PT. Basuki Rahmanta Putra - Minarta (KSO) as contractor and PT. Yodya Karya - PT.Bina Karya - PT. Intimulya Multikencana (KSO) as supervision consultant.

Meanwhile, Package 2 is built along 1.7 km for floodway excavation and 2.3 for existing excavation as much as Rp 320.43 billion with a capacity of 220 m3 / second. Package 2 work is carried out under a 2015-2020 multi-year contract by PT. PP - JAKON (KSO) as the contractor and PT. Yodya Karya - PT. Bina Karya - PT. Intimulya Multikencana (KSO) as supervision consultant. (LM)

© 2024 - IDN Financials - All Rights Reserved.